Wind power History of wind power in Quebec

1975

Early work in the Research Institute 's Hydro-Québec (IREQ), with the installation of a vertical axis wind turbine 40 kW. It is no longer in office.

1977

Installing an experimental wind vertical axis to 230 kilowatts Islands Magdalen with the collaboration of the National Research Council (NRC) and IREQ. This wind turbine is no longer in office.

1986

Installing a horizontal axis wind turbine of 65 kW at Kuujjuaq (autonomous system). The turbine has since been dismantled. She now serves as the training college of the Gaspésie-Îles.

1987

Aeolus experimental project using a 4 MW wind turbine vertical axis rotor with a height of 96 m and a diameter at the equator to 64 m. This project was conducted in collaboration with the NRC. Wind operated commercially from March 1988 to April 1993, producing approximately 12,000 MWh. This wind turbine is no longer in office.

1987

Testing of the wind-diesel Twinning Center wind test Atlantic Island Prince Edward Island.

1995

Together with the Ministry of Natural Resources of Quebec (MNR), the University of Quebec at Rimouski and consulting firm Wind Economics and Technology Inc. (WECTEC), development of a wind map from known data to determine the wind potential of Quebec.

1997

Starting the program Hydro-Québec wind measurement specifically focused on the production of wind energy with four towers. Meanwhile, the DNR install other wind measurement towers.

1998

MNR transfer the responsibility of the entire measurement program winds.

1998

Commercial operation of the first phase of the Energy Project Nordais in Cap-Chat, consists of 76 wind turbines of 750 kW each.

1999

Commercial operation of the second phase of the Energy Project Nordais in Matane, consists of 57 wind turbines of 750 kW each.

2001

Transfer to Hydro-Québec of Matane wind test consisting of three wind turbines of 750 kW each bench.

2001

Publication of the Strategic Plan 2002-2006 's Hydro-Québec indicating that the company intends to support the development of wind power in Quebec by a targeted repurchase program of up to 100 MW per year.

2002-2004

Signature by Hydro-Québec Production of purchase contracts for wind electricity from independent power producers, for a total of almost 500 MW. Hydro-Québec Production and plays a leading role.

2003

In the wake of a decision of 5 March 2003 by the Government of Quebec, launched by Hydro-Québec Distribution in May 2003, a first tender for the acquisition of 1,000 MW of power produced from wind turbines. The contracts were awarded in October. The selection took into account the lowest unit cost, including transportation.

2005

Launched by Hydro-Québec Distribution of a second tender for the acquisition of 2,000 MW of wind energy.

2008

Contracting in the second tender for the acquisition of 2,000 MW of wind energy.

2009

Launched by Hydro-Québec Distribution of a tender for the acquisition of two separate blocks of 250 MW of electricity from wind, one from Aboriginal projects and other community projects, a total installed capacity of 500 MW.